Large Industrial Rate Schedule (con't) |
|
| |
|
|
At the Customer's request, NB Power will supply, own and maintain the substation
facilities from the high voltage switches to the low voltage terminals of the
step-down transformers, provided such transformation satisfies NB Power
standards. The charge for such Rental Facilities is 1 2/3% per month of the
installed costs. The Customer will supply the low voltage switch gear, concrete
substation foundation pads and necessary protective fencing.
|
Rental
Charges |
| |
|
|
At the discretion of NB Power, electricity may be supplied at a primary service
voltage between 4 kV and 25 kV. In such cases, the monthly demand and energy
consumption will be increased by 1 1/2% to compensate for transformation
losses.
|
Losses
Charge
|
| |
|
|
When a Customer is provided service at voltages less than 69 kV, the Customer
will also be charged an "equivalent kVA rental" charge. The equivalent kVA charge is the Customer's kVA demand
multiplied by $1.24 per kVA per month. |
Transformation
Charge
|
| |
|
|
A Customer supplied at the large industrial rate is required, and is deemed, to
have entered a firm contract providing for the payment of the rate, for an
initial term of five (5) years, in the case of a Customer considered by NB
Power to be a new Customer, and for an initial term of one year for a Customer
considered by NB Power to be an existing Customer. The contract will continue
thereafter on a firm basis subject to termination by either the Customer or NB
Power at the end of the initial term, or any date thereafter by either party
giving at least twelve months' notice in writing.
When a Customer's operations are jeopardized because of a failure of its
electricity generating equipment, the Customer can apply to suspend any portion
of its curtailable power contract and/or firm up all or part of interruptible
purchases for a period of at least six months and not more than one year.
|
Contracts |
| |
|
| The metering point shall be at or near the transmission line
terminals (69 kV or above). |
Metering |
| |
|
|
table of contents | back
n1 | n2 |
n3 | n4 | n5 |
n6 | n7 | n8 |
n9 | n10 | n11 |
n12 | n13 | n14 |
n15 | n16 | n17 |
n18 | n19 | n20 |
n21 | n22| n23 |
n24 | n25 | n26 |
n27
|
next |
|
|
|
|
|