Skip to main content
Search Menu

 

Our commitment to our customers

NB Power’s top priority at this time is providing safe and reliable service to customers’ homes, businesses and communities so they can focus on what matters most.

We understand that New Brunswickers may have difficulty paying their bills due to illness, job loss, or requirements to self-isolate as result of this pandemic. Click here to learn more about the steps we’re taking to help support our customers.

In order to do our part to help contain the spread of COVID-19, we have moved our operations to essential services only. This includes emergencies, outage restoration, moving requests and essential water heater services. Please call us at 1 800 663-6272 for support with these essential services - our team remains available to assist you.

 

 

It is very important for us as New Brunswickers to do our part to help contain the spread of COVID-19.

In support of the COVID-19 response here in New Brunswick, NB Power has moved to essential services only. To learn how NB Power can help you during these unprecedented times, click here.

Since NB Power is the delivery agent for New Brunswick’s energy efficiency programs, this means that all programs have been suspended until further notice and we will not be accepting new registrations at this time.

Frequently Asked Questions (FAQs) for current program participants have been added to each program section.

During this challenging time, our commitment to our fellow New Brunswickers remains strong. We will continue to provide safe and reliable service for your homes, businesses and communities so you can focus on what matters most.

Read more

 

What happened yesterday to cause an all-day outage in Moncton and Riverview?

January 21 2018, 15:26 PM

What happened yesterday to cause an all-day outage in Moncton and Riverview?

 Early morning yesterday a large number of customers in the Moncton and Riverview areas were impacted by a transmission outage. Many customers have asked us why this outage happened and why did it take so long to restore power.

Restoration work requires a sequence of events that must take place in a specific order before the next task can occur. Many things can affect the timing of the sequence, like access to location, needing specialized equipment etc.

In yesterday’s case, an equipment fault happened in a remote location at an intersection of two transmission lines feeding three separate substations. Transmission lines feed the distribution substations that feed the distribution lines which in turn, feed into homes and businesses.

A transmission outage – like we saw on Saturday – is more difficult to address and results in larger outages. Crews were dispatched but given the remote location of the fault, more time was needed to get to the site, find the fault, bring in specialized equipment like off-road machinery, excavator, crane etc.

The initial plan was to make necessary repairs at the source of the issue, so crews outlined a plan to make the repairs, obtained work permits, brought in the heavy machinery and resources. Unfortunately, crews ran into some difficulty executing the original plan and decided to manually reconfigure the transmission circuit, isolating the damaged portion and try and energize the transmission line from another source. Once this work was done on the transmission lines, crews then needed to focus on restoring the impacted substations.

Transmission lines need to be energized before the distribution lines can be re-energized. While crews were working on the transmission lines, other crews were working to get the distribution lines ready to pick up the load once re-energized.

During this time our website displayed incorrect information regarding customers’ estimated restoration times and total number of customers impacted by the outage. We apologise for this. In cold winter months, when the power has been out for a long period of time, we can experience what is called “cold load pickup” meaning the grid is overloaded when it’s restored, and by design in order to protect itself from damage, will go out again. Some of our customers may have experienced one of these “cold load pickup” outages yesterday. Most customers were restored by 9 pm last evening.

As you can see, power restoration is not a simple task but we can assure you our crews were working as fast as possible to rectify the situation and we absolutely understand this was not an easy situation for customers, especially in winter months. We thank you for your patience.

 