Skip to main content
Search Menu

 

Our commitment to New Brunswickers

We’re committed to serving our communities. As the COVID-19 situation in New Brunswick evolves, we’ll continue to adjust and expand our services accordingly, while respecting physical distancing and safety protocols.  
 
Find out how we’re supporting our customers, and see which services remain suspended.

 

 

 

It is very important for us as New Brunswickers to do our part to help contain the spread of COVID-19.

As the COVID-19 situation in New Brunswick evolves, we’ll continue to adjust and expand our services accordingly. Our Commercial and Industrial energy efficiency programs, as well as our New Home Energy Savings Program are open for new registrations. The remainder of our programs remain suspended until further notice due to the in-home nature of this work.

 

H. Extension of Facilities - Overhead


Rate Schedules and Policies Manual

H. Extension of Facilities - Overhead

RSP H-6

table of contents | back h1 | h2 | h3 | h4 | h5 | h6

next

Extension of Transmission Facilities

NB Power will extend the transmission system to the Customer's substation terminating structure. The Customer will provide a guarantee for the total cost of the transmission system expansion less any contribution to capital made in accordance with Attachment K of NB Power’s Open Access Transmission Tariff (OATT). Guarantees may be in the form of cash, letters of guarantee from Chartered Canadian banks or trust companies, bearer bonds guaranteed by either the Government of Canada or the Province of New Brunswick, or surety bonds issued by a duly authorized company.

This guarantee is reduced each year by an amount equal to 10% of the total of the previous twelve months' paid bills for power and energy. If the guarantee is not fully refunded within the first five (5) years, NB Power will demand payment for the remaining amount of the guarantee.

When the guarantee is cash, the interest rate shall be equal to the prime rate, as quoted by the Royal Bank of Canada, minus two per cent (2%).