The charge for non sufficient funds is $15.00.

Non Sufficient Funds Charge

The Construction Charge is the estimated cost times the contribution ratio of 100%.

Extension Of Overhead Facilities Charges

Type of Original Contribution

Type of
New Account
Connected

Single Phase

Three Phase

Extension Of Overhead Facilities Refunds

Single-Phase

90 meters times the average per meter
Construction Charge

90 meters times half of the average per meter
Construction Charge

Three-Phase

90 meters times the average per meter
Construction Charge

90 meters times the average per meter
Construction Charge