Skip to main content
Search Menu

Fundy Isles Transmission Power Line Project

The Fundy Isles Submarine Cables provide electricity to Deer Island to Campobello Island, Campobello Island and Grand Manan Island.   The original cables were installed in 1978 and are nearing the end of their useful life.

In order to maintain a reliable feed to the Fundy Isles NB Power proposes to install new cables between Deer Island and Campobello Island and between Campobello Island and Grand Manan Island while the existing cables remain in service.

The new cables will be rated higher than the existing to allow for the potential addition of future renewable energy projects.

The existing cables will remain in service for the foreseeable future. No decision with respect to their removal has been taken. We are currently assessing the different options.

 

Below is a timeline for the proposed project:

Project Activities Timelines

EIA Submission

January 2018

EIA Determination

September 2018

Cable Manufacture

December 2018 - June 2019

Land Based Work - HDD

March 2019 - July 2019

Land Based Work - Termination sites

October 2018 - October 2019

Cable Installation

August 2019

Cable Terminations

September - October 2019

In-Service Date

November 2019

 

On January 26, 2018 NB Power Corporation registered the project with the Department of the Environment and Local Government in accordance with Section 5(1) and Schedule “A” of the Environmental Impact Assessment Regulation – Clean Environment Act.