Skip to main content
Search Menu

New Brunswick/Nova Scotia Transmission Reliability Project

transmission lines

Project Background

This project consists of a new 345 kilovolt (kV) transmission line from New Brunswick to Nova Scotia to increase energy reliability for Nova Scotia. This upgrade would allow Nova Scotia Power more operational flexibility and greater opportunity to integrate renewable, clean energy into their system into the future. 

Currently, there is only one 345 kV transmission line feeding into Nova Scotia from New Brunswick.

A new transmission line would be approximately 65 km in length and run from an expanded terminal near Salisbury, to an expanded terminal in Memramcook, and then to the New Brunswick-Nova Scotia border. It would run parallel to the existing transmission line.

Project Benefits

This additional line and improved capacity would allow both New Brunswick Power and Nova Scotia Power to continue advancements towards the clean energy roadmap as both utilities continue to work towards a path to net zero and phasing out of fossil fuel generating sources in the years to come.

Current Status

Since June 2022, teams of qualified biologists have worked on NB Power Corporation’s behalf to conduct exploratory field work to examine the feasibility of adding a new 345‐kilovolt transmission line adjacent to the existing transmission line corridor.

We continue to conduct field surveys, including geotechnical and archaeological investigations, to support the Environmental Impact Assessment and project viability. These studies will provide material to support future engagement and discussions with landowners, stakeholders and First Nations.

These field studies are non-intrusive in nature. Careful archeological and environmental protocols are being followed and are observed by Mi'gmawe'l Tplu'taqnn Inc. (M.T.I.) and NB Power’s First Nations Field Monitor.

Baseline environmental data is being collected to support the potential of an additional transmission line; however, any new transmission line installation would be subject to regulatory review and approval. 

A series of public and stakeholder engagement sessions are planned for the summer of 2023, as well as a regulated Environmental Impact Assessment under the Province of New Brunswick process will be carried out and registered in the fall of 2023.

Proposed Schedule

Project Activities Timelines
Engagement with First Nations, public, and Stakeholders Ongoing throughout the project 
Complete field studies and EIA registration  Fall 2023
Planning and Engineering Summer 2024
Construction activities commence  Fall 2024

Open Houses

Open Houses will be held from 4 to 8 p.m. in the following locations:

Tantramar
Tuesday, July 11, 2023
Tantramar Veterans Memorial Civic Centre, 182 Main Street

Memramcook
Wednesday, July 12, 2023
Club d’âge d’or de Memramcook (Berceau), 409, route la Vallée

Fundy Albert
Thursday, July 13, 2023
The Big Dreams Club, 19 Kierstead St., Lower Coverdale

Salisbury
Wednesday, July 19, 2023
Salisbury Lions Club, 63 Peter Street